Project Summary

Project Scope:

Delivered the end-to-end design, supply, installation, testing, and commissioning of the following systems for the Elmina Tapir Hyperscale Data Center:

• Site Earthing System

• Comprehensive Lightning Protection System (LPS)

• Real-time Tokai Lightning Warning System (LWS)

The works encompassed:

• Detailed earthing and lightning protection engineering design

• Supply of Tokai high-conductivity, corrosion-resistant, IEC-compliant materials, including earth electrodes, conductors, bonding components, and accessories

• Installation in accordance with approved method statements and international best practices

• Full testing, commissioning, and certification, including earth resistance measurements, continuity tests, and system functionality validation

All materials and systems were fully compliant with MS IEC 62305:2022/2024, IEC standards, OSHA, and data-Center-grade safety and reliability requirements, ensuring long-term operational integrity and protection of critical infrastructure.

Related projects

Prime Minister’s Residence Putrajaya
Prime Minister’s Residence – Putrajaya

Prime Minister’s Office Putrajaya
Prime Minister’s Office – Putrajaya

Istana Alam Shah Klang
Istana Alam Shah – Klang